0%
0 votes, 0 avg

PROJECT MANAGEMENT EXAMINATION

Welcome to Your Examination Portal.  We wish you all the best as you kick start a wonderful career with us

ONLINE EXAMINATIONS

The online assessment is taken on completion of the training material. You will be asked 100 multiple choice questions with a pass mark of 50%. The answers are marked automatically so you will instantly know whether you have passed. If you don’t pass don’t worry! You can take the Exam again

Whether you are a student on our platform or not we encourage you to email your enquires to our friendly team if you need help with anything at [email protected]

 

REGISTER TO START YOUR EXAMINATION

1 / 100

CIPM. Which of the following is the most efficient means of product quality inspection

2 / 100

CIPM.  Project integration management involves all the following processes except

3 / 100

CIPM    Which of the following conflict resolution techniques will generate the MOST lasting solution?

4 / 100

Question - 27 As a project manager you understand the importance of identifying all relevant stakeholders, their interest and influence and their needs and expectations. You have been assigned to handle a large construction project. You decide to do a thorough stakeholder analysis and you identify Bob and Kelly. Based on your interactions and analysis - you know that Bob wields a lot of authority and also has a huge interest in the project. Kelly too wields a lot of power but is largely uninterested. You decide to plot them in a Power / Interest grid to help determine how you would manage these stakeholders. Which of the following is the best approach to handle these two stakeholders?

5 / 100

Question - 14 You are developing strategies to effectively engage stakeholders throughout the project life cycle. What is process you are working on ?

6 / 100

CIPM  Extensive use of ----- communication is most likely to aid in solving complex problems.

 

7 / 100

CIPM  When checking the calendar of a team member to schedule a meeting, you see she has scheduled a meeting with a key stakeholder that you were not informed of. The best approach would be to:

 

8 / 100

CIPM. A project manager has been working on a project for six months with the same team yet the team still shows a lack of support for the project. The best thing for the project manager to do would be to?

9 / 100

CFM7. Most common cause of conflicts in a project is

10 / 100

CIPM. Which of the processes of procurement supports the close product or phase process?

11 / 100

CIPM. The sending or conveying of information from one place to another is the process of:

12 / 100

CIPM. Projects are undertaken at all levels of the organization?

13 / 100

Question - 45 Of the following types of contracts - which has the HIGHEST risk for the buyer ?

14 / 100

Question - 41 You are the project manager and decided to outsource a part of the project to a vendor. The vendor discovered some issues that impact the cost and schedule of its work. How does the vendor update the

Question - 41 You are the project manager and decided to outsource a part of the project to a vendor. The vendor discovered some issues that impact the cost and schedule of its work. How does the vendor update the agreement?

15 / 100

CFM 17 -The HVAC systems designed with a capacity is based on ________________

16 / 100

Question - 36 As a manager on a project you have identified and created the WBS and WBS Dictionary. You now plan to ensure that each deliverable gets the blessings of your stakeholders and sponsors. Which process are you planning to perform?

17 / 100

CFM 17 -The HVAC systems designed with a capacity is based on ________________

18 / 100

CIPM. What is Team Development?

19 / 100

CFM1. People negotiate daily, often without considering it a negotiation

20 / 100

CIPM. Firm fixed price contracts stand for

21 / 100

CIPM. Which of the following is NOT an example of a type of schedule report?

22 / 100

CFM11. What is an important aspect of service layout?

23 / 100

CIPM   A rough order of magnitude estimate is made during which project management process group?

 

24 / 100

Question - 37 Which of the following best describes Expectancy theory?

25 / 100

CFM15.

What is the advantage of good layout design in the case of service organizations?

26 / 100

CIPM. One  of  the following is NOT among tools & techniques used to conduct procurements

27 / 100

CIPM. Some organizations are now using 6 Sigma for quality control compared to the usual:

28 / 100

Question - 18 You have just completed developing the Schedule Network Diagram for a project that deals with building supersonic state of the art Jet planes. You have identified your critical path which includes building a wind tunnel. You see that in addition there is another path which deals with building the tail of the plane - whose duration is close to the critical path. You also notice considerable floats on the other paths. You now need to assign resources to the tasks - you have a few team members who are highly skilled and a team of resources who are relatively inexperienced. What would be the best course of action while assigning resources

29 / 100

Question - 14 You are developing strategies to effectively engage stakeholders throughout the project life cycle. What is process you are working on ?

30 / 100

CIPM. Your new product development project has resulted in a highly successful new product. The property, equipment, materials, and personnel of your project are now being integrated into the functional organization. Your project is being terminated by:

31 / 100

CIPM. -------------------------Is an enterprise environment factor which can affect the availability of resources and influence how projects are conducted

32 / 100

CIPM. The three major types of communication are:

33 / 100

CIPM. Who is responsible for risk identification, risk quantification, risk response development, risk Monitor and Control?

34 / 100

CIPM. Which acronym stands for cost plus award fee contracts?

35 / 100

CIPM   In which project management process group is the detailed project budget created?

 

36 / 100

CFM 21 - In order to best serve user needs, facility standard must be ______________

37 / 100

CIPM. -------------------------- Is a schedule network analysis technique that modifies the project schedule to account for limited resources

38 / 100

Question - 22 You are the project manager and have decided to outsource a part of the project to a vendor. You have offered a bonus to the vendor if the work is completed in two months. This is an example of _____________.

39 / 100

CIPM.     A fundamental tool used by the project manager to deliver the successfully is known as

40 / 100

CIPM  A buyer extends a formal invitation that contains a scope of work that seeks a response that will describe the methodology and results that will be provided to the buyer. This is called:

41 / 100

CIPM. Which of the following Project Scope Management processes involves subdividing the major project deliverables into smaller, more manageable components?

42 / 100

CIPM. As project manager you should dedicate a primary focus to:

43 / 100

CIPM. The review of key deliverables and project performance at the conclusion of a project phase is called

44 / 100

CFM13.

Which factor influence location for a service organization?

45 / 100

Question - 50 Project Team has created sub plans for each knowledge areas in project plan. These plans are called:

46 / 100

CIPM. The work that needs to be accomplished to deliver a product, service, or result with the specified features and functions is referred to

47 / 100

Question – 16 As a project manager you understand the importance of identifying all relevant stakeholders , their interest and influence and their needs and expectations. You have been assigned to handle a large construction project. You decide to do a thorough stakeholder analysis and you identify Laura and Sean. Based on your interactions and analysis - you know that both Sean and Laura are low in the pecking order so they do not wield any significant authority or power. However where it differs is in their interest in the project. Laura has a lot of interest while Sean is disinterested. You decide to plot them in a Power / Interest grid to help determine how you would manage these stakeholders. Which of the following is the best approach to handle these two stakeholders?

48 / 100

CIPM. Which of the following statements concerning contract type is correct?

49 / 100

Question - 33 You have been assigned to manage a project that deals with setting up a railway line connecting two cities. The project is complex with a lot of contracting involved. You and experts in your organization are evaluating if the rail line alignment machinery should be purchased outright or if it would be better to lease. The cost of leasing the equipment is 1200 $ per day while the cost of an outright purchase is 96000 $ and a daily cost of 200 $.The duration of laying out the railway lines is scheduled to be an activity duration of 150 days. Should you purchase the machinery or be leased - which option would be more economical?

50 / 100

CFM 25 - ______________ can be defined as an interdisciplinary business function has the objective to coordinate demand and supply of facilities and services within public and private organizations

51 / 100

CIPM. Your new product development project has resulted in a highly successful new product. The property, equipment, materials, and personnel of your project are now being integrated into the functional organization. Your project is being terminated by:

52 / 100

CIPM. Which among the following is NOT a method of reaching a group  decision?

53 / 100

CIPM. The contract change control system  is integrated with  _____

54 / 100

CIPM   The WBS and WBS dictionary are completed. The project team has begun working on identifying risks. The sponsor contacts the project manager, requesting that the responsibility assignment matrix be issued. The project has a budget of U.S. $loo,ooo and is taking place in three countries using 14 human resources. There is little risk expected for the project and the project manager has managed many projects similar to this one. What is the next thing to do?

 

55 / 100

CFM14.

Which crucial factor affects the layout?

56 / 100

CIPM.  Includes the processes required to ensure that the project include all the work required, and only the work required, to complete the work successfully

57 / 100

Question - 44 Which of the following activities is not performed as a part of Project Closure?A. Ensure all the deliverables as per contract are met

58 / 100

Question - 39 You are managing a project which involves building software for the aeronautical domain. The nature of the work is complex and needs a lot of research. During Quality assurance both the development team and testing team suggest that the quality assurance process be changed to also include White Box testing and not only rely on Black box testing. The team wants to make this shift in approach as they believe this would lead to better quality of deliverables - what is the best course of action ?

59 / 100

Rather than use Triangular Distribution while doing Three Point Estimation you choose to use Beta Distribution. Based on your analysis and understanding you are confident that the project would be completed with a total cost of 108,000 $. You also estimate that a best case estimate would be 90000 $ while a worst case scenario would result in the costs incurred to shoot up to 138000 USD. What would the Three point Cost estimate be using Beta Distribution?

60 / 100

CIPM. The process of creating, collecting, distributing, storing, retrieving and ultimately disposition of project information in accordance with the communications management plan is called

61 / 100

Question - 34 Earned Value Analysis is used to measure performance based on following parameters:

62 / 100

Question - 35 Which of the following statements are not true regarding Validate Scope ?

63 / 100

Question - 42 As a manager on a project your key outlook is to ensure that the project delivers within the scheduled timelines with minimal rework and customer delight. For some time now the project work is proceeding smoothly with a CPI and SPI a perfect 1.One of your team members approaches you and indicates that she might possibly need a long vacation on personal grounds. She indicates this could possibly occur in two months from now. You look up the schedule and as luck would have it - this team member happens to be scheduled to execute activities which are on the critical path - and her absence in two months’ time would cause a delay in schedule. You decide to take some action and reschedule task allocation to ensure that this team member is not planned to work on any of the critical path activities. What did you just do?

64 / 100

Question - 20
Your company policy allows accepting gifts from customers within certain limit. Your customer is giving you a gift which is beyond the limit of your company policy. You have given a gift to the customer's representative already which has similar in value. What should you do?

65 / 100

CFM 24 - Which of the following explain the need for facility location selection?

 

 

66 / 100

CIPM. Pareto Analysis, cause and effect diagrams and flow charts are used in quality.

67 / 100

Question - 25 What is the BEST use of a Work Authorization System?

68 / 100

Question - 25 What is the BEST use of a Work Authorization System?

69 / 100

Question - 40 The Scope Baseline consists of the following:

70 / 100

CIPM. Which of the following is NOT a method of government procurement?

71 / 100

CIPM. Network planning methods(PERT/CPM/PDM):

72 / 100

CIPM -Earned value can be described as:

73 / 100

Question - 47 Using historical information to perform estimating is also called _______ estimating.

74 / 100

CIPM. One of the following is NOT a process of project time management.

75 / 100

Rather than use Triangular Distribution while doing Three Point Estimation you choose to use Beta Distribution. Based on your analysis and understanding you are confident that the project would be completed with a total cost of 108,000 $. You also estimate that a best case estimate would be 90000 $ while a worst case scenario would result in the costs incurred to shoot up to 138000 USD. What would the Three point Cost estimate be using Beta Distribution?

76 / 100

CFM 26 - Recycling is the reuse and reclamation/recovery of premises or environment

77 / 100

CIPM.   All the following are project process groups except

78 / 100

CIPM. When you are closing out a project, what must you do?

79 / 100

CIPM  Manage Stakeholders is a part which of the following process group:

 

80 / 100

Question - 40 The Scope Baseline consists of the following:

81 / 100

CFM 26 - Recycling is the reuse and reclamation/recovery of premises or environment

82 / 100

CFM13.

Which factor influence location for a service organization?

83 / 100

CIPM    A project manager has assembled the project team, identified 56 risks on the project, determined what would trigger the risks, rated them on a risk rating matrix, tested their assumptions and assessed the quality of the data used. The team is continuing to move through the risk management process. What has the project manager forgotten to do?

84 / 100

CIPM   What is critical path?

85 / 100

Question - 45 Of the following types of contracts - which has the HIGHEST risk for the buyer ?

86 / 100

CFM 15 - What is the advantage of good layout design in the case of service organizations?

87 / 100

Question - 36 As a manager on a project you have identified and created the WBS and WBS Dictionary. You now plan to ensure that each deliverable gets the blessings of your stakeholders and sponsors. Which process are you planning to perform?

88 / 100

.All  the followings are the out puts of administer procurement except on

89 / 100

CFM 15 - What is the advantage of good layout design in the case of service organizations?

90 / 100

CIPM. Which of the following is NOT an input of plan procurement?

91 / 100

Question - 38 A friend of yours approaches you seeking advice. She indicates she has offers from two organizations. Her role in one of the organization is that of a project Co-ordinator while in the other organization her role is that of a Project expediter. She is not quite clear of the difference between the two roles and seeks your advice. Which of the following statement is true

92 / 100

Question – 16 As a project manager you understand the importance of identifying all relevant stakeholders , their interest and influence and their needs and expectations. You have been assigned to handle a large construction project. You decide to do a thorough stakeholder analysis and you identify Laura and Sean. Based on your interactions and analysis - you know that both Sean and Laura are low in the pecking order so they do not wield any significant authority or power. However where it differs is in their interest in the project. Laura has a lot of interest while Sean is disinterested. You decide to plot them in a Power / Interest grid to help determine how you would manage these stakeholders. Which of the following is the best approach to handle these two stakeholders?

93 / 100

CIPM. Which of the following acronyms stand for fixed price with economic price adjustment contracts

94 / 100

CFM5. The second most valuable resources is the ________________________

95 / 100

Question - 30 You have received a number of seller responses for contracting work related to setting up office cubicles. One of the bids received happens to be from a very good friend of yours. You know she has done good work in the past. What should be the BEST course of action?

96 / 100

CIPM. The receiver filters messages based on all but the following:

97 / 100

CFM 22 - Which of the following is the most important function for a project management success?

98 / 100

CIPM   You are a project manager who was just assigned to take over a project from another project manager who is leaving the company. The previous project manager tells you that the project is on schedule, but only because he has constantly pushed the team to perform. What is the FIRST thing you should do as the new project manager?

 

99 / 100

CFM12. Which factor influences location strategy for facility location?

100 / 100

CIPM  A project manager is faced with making a decision about a risk that the team has identified. The risk involves the design of a bicycle. It has been found that the neck of the bicycle, where the steering bearing is located and the two supporting bars of the frame come together, will corrode in a high salt environment. If this takes place the neck may fail and injure the rider. The project team decides that the design of the bicycle should be modified by using corrosion resistant materials in the design of the neck. This will eliminate the risk from consideration. This technique is called:

 

Your score is

0%